Metro construction with early contractor involvement
Metroselskabet has tendered the construction of two new metro stations in Nordhavn, with a focus on early contractor involvement. We have been selected as the turnkey contractor and will work with Rambøll and Cobe on the development, design and construction of the project.
The project will extend the metro network by continuing the M4 line from Orientkaj Station to the two new stations at Levantkaj and Nordhavn C (near Tunnelfabrikken), both of which will be built as elevated stations. Passengers at the two new stations will have direct access to the inner city districts and transport hubs, with a travel time of approx. 7 minutes from the terminus at Nordhavn C to Østerport and approx. 14 minutes to Copenhagen Central Station.
Construction is expected to begin in 2027, with completion scheduled for 2030.